Building the crossing
Overview
- Section 1: Foreword
- Section 2: What is the Lower Thames Crossing?
- Section 3: The story so far
- Section 4: Why the Lower Thames Crossing is so important
- Section 5: The route - Design changes
- Section 5: The route - South of the river in Kent
- Section 5: The route - The crossing
- Section 5: The route - North of the river in Thurrock and Essex
- Section 6: Local communities, landscapes and the environment
- Section 7: Building the crossing
- Section 8: Using the Lower Thames Crossing
- Section 9: Consultation and development consent
- Section 10: How to have your say
- Section 11: Events and further information
When construction will take place
We will build the new roads and tunnel in phases, which will be the most efficient way of working so that different elements of the project can be completed at the same time. Our suggested plans, alongside indicative timings, are below:
More Information
* the start of the year depends on consent
We will carry out most of the work between 8am and 6pm on weekdays (excluding bank holidays), and between 8am and 4pm on Saturdays. These are standard hours for construction projects up and down the country, although crews may work for up to an hour before and after to prepare and close the site. From time to time we may also have to do some maintenance work on Sundays. We will work closely with highways teams from the local authorities in each affected area to identify the best working times for each site, so these times may vary.
As with any project of this scale, we will have to do some of the work at night. For example, where possible we will work on existing roads overnight to reduce disruption to drivers going about their daily journeys. Tunnel construction will be a 24-hour operation throughout.
Most of the construction work will take place during the day
Getting ready for construction
Before the main construction work can begin, we need to acquire land and prepare the site. This includes:
- diverting public rights of way and utilities
- creating new habitats
- carrying out flood avoidance measures
- species relocation
- removing vegetation as necessary
- making any contaminated land safe
- completing detailed surveys about the land and surrounding area
- archaeology
More Information
Have your say
To comment on our construction plans, answer question 11 on the response form.
Next we will prepare individual sites for construction. We expect to tackle the most complex sites, including the tunnel, M25, A13 and A2 junctions, first.
Find out more
To find out more about construction, see Approach to Design, Construction and Operation.
Tunnelling work
It is likely to take around six years to build the tunnel. During this time, we plan to have a construction site next to the northern entrance. This will include equipment for producing the precast concrete for the tunnel lining, a water treatment system and a temporary substation to provide power for the tunnelling machines.
More Information
Tunnelling work could begin from either the northern or southern entrance. Based on the information we currently have, we expect to begin near the northern entrance. Two machines will excavate the tunnel, which will then be lined with precast concrete segments.
On average, a tunnel boring machine excavates at a rate of between 50 and 125 metres a week, depending on the model.
This is very similar to the tunnel boring machine we plan to use
This project is an enormous undertaking using the most sophisticated tunnelling equipment in the world. It will mean underground construction and activity will take place 24 hours a day, seven days a week to complete the tunnel as soon as possible. It is standard practice during 24- hour operations to put in place special measures such as noise barriers to keep potential impacts to a minimum.
During construction, we will make sure we keep residents, businesses and road users informed of planned works in advance and share information on progress.
Machines will excavate the tunnel, which will then be lined with precast concrete segments
Building the roads
We will build the new roads, junctions, bridges and underpasses at the same time as the tunnelling work. Most of this will be done during standard hours as we discussed earlier in this chapter.
The new road will connect the M2/A2 in Kent with the M25 south of junction 29 in Essex, crossing the A13 north of Chadwell St Mary. To connect with these existing roads, as well as the A1089, we will construct new junctions and will have to carry out some work on these roads as well. This includes improvements such as road widening for the M2/A2 and M25.
How we will use other public roads
We always try to keep road closures during construction to a minimum. Where diversions, temporary traffic lights or lane restrictions are planned, we will give road users and people living nearby plenty of notice so they can consider alternative routes or travel arrangements.
More Information
A significant number of HGV journeys will be needed to transport material to and from the sites. An estimate of the average number of HGV journeys per month for each of the five construction areas is shown on pages 110-113, with each HGV journey making one trip to the sites and another away from the sites. The maps also show the areas where construction traffic may travel. The exact routes will be agreed at a future stage of the project.
We will carefully plan which roads construction traffic will use to reach our sites
We will carefully plan which roads construction traffic will use to reach our sites. Where there are no roads to the construction site, we will build access roads connecting to the existing network. We will work with the local highways authorities to identify routes that minimise the impact on local roads and communities.
We will build new roads, junctions, bridges and underpasses at the same time as the tunnelling work Juxtapose images
Roads to the construction sites
The crossing is split into four construction areas labelled A-D. The following maps show the roads that construction vehicles are likely to use the each of the sites. The exact routes will be carefully planned closer to the time.
(Click on an arrow below the map to view all the maps)
The impact of construction on local roads
Most construction materials will be transported to the sites by road, which will have some impact on the road network and road users. At locations where new connections to the network will be created, we will carry out traffic management to segregate the construction sites from road vehicles.
More Information
Some local routes will be affected by construction, with some roads temporarily closed and others having temporary diversions, traffic lights and/or lane restrictions. We will provide advance warning so people can look at alternative routes or travel arrangements.
The predicted impacts on specific roads are classified as follows:
- High: road may close, with possible diversion and/or lane restrictions.
- Medium: road remains open, with temporary diversion, traffic lights and/or lane restrictions.
- Low: road remains open, with temporary diversion, traffic lights and/ or lane restrictions.
Road affected | Planned construction | Possible impact |
Brewers Road | Replacement of bridge carrying Brewers Road over M2 | High |
Thong Lane | Replacement of bridge carrying Thong Lane over A2, plus new bridge carrying Thong Lane over LTC | Low |
A2 (near LTC junction) | New bridge and tunnel at LTC junction with A2 | Medium |
Station Road | New viaduct to carry LTC over Station Road | Low |
Muckingford Road | New bridge to carry Muckingford Road over LTC | Low |
Hoford Road | New bridge to carry Hoford Road over LTC | Low |
Brentwood Road | New bridge to carry Brentwood Road over LTC | Low |
Hornsby Road | New bridge to carry Hornsby Road over LTC | Low |
Heath Road | Northern end of Heath Road closed due to A1013 works | Low |
A1013 | New bridges to carry A1013 over LTC, A13 and A1089 | Medium |
A1089 | New viaduct and bridges at LTC junction with A13 and A1089 | Medium |
Road affected | Planned construction | Possible impact |
Baker Street | New viaduct and bridges at LTC junction with A13 and A1089 | Low |
A13 | New bridges at LTC junction with A13 and A1089 | Medium |
Rectory Road | Replacement of bridge carrying Rectory Road over A13 | Low |
Stifford Clays Road | New bridges to carry Stifford Clays Road over LTC and slip roads | Low |
Green Lane | New bridge to carry Green Lane over LTC | Low |
B186 North Road | New bridge to carry B186 North Road over LTC | Medium |
M25 (at LTC junction) | New structure to take LTC under M25 | High |
Ockendon Road | New bridge to carry Ockendon Road over LTC and M25 | Medium |
St Mary’s Lane | Replacement of structure taking St Mary’s Lane under M25 | Low |
M25 junction 29 | Widening of Codham Hall Viaduct carrying M25 over A127 | High |
A127 | Widening of Codham Hall Viaduct carrying M25 over A127 | Low |
Our construction sites will be operated to the highest standards in the industry
Construction sites
More Information
Each construction site will have temporary buildings and storage areas, and will include offices, space for equipment and materials, parking and staff facilities. Some sites will include specialist zones, such as the tunnel construction area at the north entrance site. The five main sites are shown on this map, and there will also be several smaller sites.
(Click on the map to reveal the construction sites)
Managing the construction impacts
Building the new route will affect the local environment. Wherever possible, we are determined to protect, and look for opportunities to enhance, the local environment and improve biodiversity.
More Information
We will make sure we protect species and habitats
We are already carrying out extensive surveys, monitoring and investigations, which are helping us to understand how the crossing might affect air quality, noise and the landscape. This information is helping us to find ways to reduce these impacts. Once all that information has been fully assessed, we will publish the findings in our Environmental Statement, as part of our DCO application.
We will produce a draft Code of Construction Practice (CoCP), which we will submit with our DCO application. It will describe how we will reduce the disruption to local communities and the environment during construction and our approach to limiting noise and vibration.
Surveys will help us understand how the crossing might affect air quality, noise and the landscape
As we develop the CoCP we will work closely with specialists in the local authorities to make sure that it best reflects the needs of their local communities
We will excavate a significant amount of material, which will be processed and reused onsite where possible. Material that cannot be reused, such as hazardous waste and contaminated soil, will be safely disposed of in line with regulations. If practical, we will transport some material that cannot be reused by river rather than by road. We are currently looking at how this might be possible. If we use the river, we may need to build a new temporary jetty or use an existing one.
To reduce construction traffic using the roads, we are considering alternatives, such as river transport, to move materials and waste to and from work sites
As with any road project, we will make sure we protect species and habitats in the area. These include great crested newt breeding ponds, reptile hibernation areas and bat breeding roosts. We will only remove vegetation during the bird breeding seasons (typically early March to late August) if absolutely necessary, and this will be overseen by an appropriately qualified ecologist.
Utilities and pylons
To build the road, high voltage electricity overhead lines, including pylons, gas pipelines and other utilities would have to be diverted across several locations in Kent, Thurrock and Essex. This would ensure we can build the road safely, with no overhead obstructions, and also allow for future maintenance.
More Information
Gas pipelines and other utilities
National Grid is the owner and operator of the transmission networks and it is they who will carry out this work.
Here are the proposed locations for overhead lines and pylons diversions, shown on the map below.
(Click on the map to reveal the locations)
There are other pylons and high voltage overhead lines, owned and operated by UK Power Networks, which will need to be diverted. The designs for these are being developed but the works involved will not be as large scale.
Have your say
To comment on changes to utilities and pylons, answer question 12 in the response form.
Gas pipelines and other utilites
National Grid has carried out onsite inspections and surveys to mark the precise routes where it needs to divert two existing gas pipelines. These are at the A2 and Claylane Wood. It has identified some preferred options.
Designs for the diversion of other pipelines carrying gas and water, and also electricity and telecoms cables, are being developed. We are working closely with the various energy, water and telecoms companies to agree how these works will be carried out.
Find out more
To find out more about utilities, pylons and gas pipelines see the Approach to Design, Construction and Operation
Paying for the project
We estimate that the cost of developing and building the Lower Thames Crossing will be between £5.3-£6.8 billion. Making the right financial decisions is vital to make sure it offers value for money for taxpayers and is affordable to the government. Our plan is for the tunnel to be publicly funded and the approach roads, including the junctions, to be privately financed.
More Information
Private finance gives us far more certainty in terms of cost and timeframes, and makes it more affordable as payment can be deferred until the crossing is open, and spread out over 25-30 years. However, given the scale of spend and the capacity of the private finance market, this option is not considered to be an efficient way to pay for the tunnel.
As with any transport project of this kind, its value for money is assessed on how much benefit it would provide, against its cost. This is called a Benefit Cost Ratio (BCR), and it assesses how much benefit a project would provide per unit of cost. A BCR of more than 1 shows that a project delivers more value than its cost. For example, a BCR of 1.5 shows that for every pound spent a project will bring £1.50 in benefits.
The Department for Transport uses six value for money categories ranging from Very High to Very Poor. The Lower Thames Crossing is currently showing Medium value for money with an estimated BCR between 1.5 and 2, which means that every pound spent is expected to bring between £1.50 and £2 in benefits.
We are working hard to make sure that every penny is spent wisely. The government holds us to account to make sure the public money we spend will provide genuine benefits. The most significant financial benefits for road users and businesses will be journey time savings and better connections.
The most significant financial benefits for road users and businesses will be journey time savings and better connections
Continue to the next section: Section 8: Using the Lower Thames Crossing
Read more
- Section 1: Foreword
- Section 2: What is the Lower Thames Crossing?
- Section 3: The story so far
- Section 4: Why the Lower Thames Crossing is so important
- Section 5: The route - Design changes
- Section 5: The route - South of the river in Kent
- Section 5: The route - The crossing
- Section 5: The route - North of the river in Thurrock and Essex
- Section 6: Local communities, landscapes and the environment
- Section 7: Building the crossing
- Section 8: Using the Lower Thames Crossing
- Section 9: Consultation and development consent
- Section 10: How to have your say
- Section 11: Events and further information
Audiences
- Anyone from any background
Interests
- Roads